Project Description

This construction project will widen John Sims Parkway to six lanes from southwest of Government Avenue to east of Bayshore Drive.  The $12.6 million project will be constructed in three phases. 
 

Phase 1

  • Construct three stormwater retention ponds.

  • Install temporary asphalt pavement for cross-overs that will be needed in subsequent construction phases.

  • Install new traffic signals.

  • Widen the westbound side of John Sims Parkway.

Phase 2

  • Widen the eastbound side of John Sims Parkway.

 

Phase 3

  • Reconstruct the raised median.

  • Reconstruct eastbound and westbound travel lanes not completed in Phases 1 or 2.

 

 